1 before

The drive needed widening to allow larger modern cars to park on the drive.

We took down the stone wall and stacked the stone at one side. Dug out the ground with an excavator and disposed of the spoil. Once dug out we poured a concrete strip foundation for the wall. We re-built the wall as before in random stone and back filled the wall with soil.

2 before3 during

The project took 1 week to carry out.